.. _label-schedule: Schedule ======== The portal software will be developed, released and deployed in two phases. **Phase 1** focuses on: - portal setup, user management, business unit management - the migration of legacy data from existing Eko Disco customer databases into the EDP - registration process of existing customers - registration process of new customers - communication with customers - completion of contracts Software deployment is **8 months** after award of contract. **Phase 2** includes: - meter reading processes - billing and payment - accounting All remaining use cases will be implemented in the second phase. Software deployment is **16 months** after award of contract.